4.7 MWp in 15 days – ib vogt completes first construction phase for the Thunpadel solar power plant

07-03-2012 10:39 PM CET | Energy & Environment

Press release from: ib vogt

4.7 MWp in 15 days – ib vogt completes first construction phase

After just 15 days of construction, ib vogt GmbH has completed the first phase of construction for the Thunpadel solar power plant in Lower Saxony, which has a rated output of 4.7 MWp. The solar power plant will be expanded to achieve a total rated output of around 10 MWp by the end of September.

Berlin, 2 July 2012: With the granting of planning permission on 13 June 2012, the first construction phase for the Thunpadel solar power plant in Lower Saxony began on the site of an old sawmill. On the same day workers began driving piles into the ground, onto which 816 mounting racks and 19,584 modules were mounted during the following 15 days. The polycrystalline modules produce a rated output of approximately 4.7 MWp. As the general contractor, ib vogt GmbH is developing, planning and realising the project.

The Thunpadel solar park is located on the site of an old sawmill south of the municipality of Karwitz in the rural district of Lüchow-Dannenberg. The site has remained unused since 2001. Thanks to the solar power plant, the former brownfield site not only has a new purpose but the local community will also benefit in future from the business tax revenues. Its close proximity to the nuclear waste storage facility at Gorleben means that the solar power plant also sets a particularly positive signal for the energy turnaround.

Work on the second construction phase will commence during the next few weeks. The completed solar power plant will extend across an area around 13 hectares in size with a future rated output of approximately 10 MWp. This will enable around 2,900 households to be supplied with electricity with simultaneous carbon dioxide savings of around 5,000 tonnes a year.

###

As a reliable EPC or EPCM partner that is internationally active, ib vogt GmbH develops, plans and realises solar power plants and photovoltaic production facilities throughout the world.
The company’s success story began in 1998 with the initial concept study for a photovoltaic factory in Germany. ib vogt GmbH offers consultancy, planning and project management services for new-build projects and existing photovoltaic production. Its area of focus includes optimising and increasing the efficiency of existing photovoltaic production facilities.
ib vogt GmbH works independently of technology and manufacturers, whereby its expertise covers the entire photovoltaic value added chain for both crystalline (ingots, wafers, cells, modules) and thin-film technology.
Since 2009, ib vogt GmbH has realised solar power plants as ground-mounted, rooftop and building-integrated systems with a total rated output of around 100 MWp. Its range of services extends from the planning, development and construction of solar power plants to their turnkey handover. Operation and maintenance of solar power plants is another service product offered by the company.

ib vogt GmbH
Helmholtzstr. 2-9
10587 Berlin
Tel: +49 30 39 74 40-0
Fax: +49 30 39 74 40- 10
Email: presse@ibvogt.com
Web: www.ibvogt.com

Press contact:
Juliane Gehrke

This release was published on openPR.

Permanent link to this press release:

Copy
Please set a link in the press area of your homepage to this press release on openPR. openPR disclaims liability for any content contained in this release.

You can edit or delete your press release 4.7 MWp in 15 days – ib vogt completes first construction phase for the Thunpadel solar power plant here

News-ID: 227816 • Views:

More Releases from ib vogt

Visit to renewable energies sector in Berlin-Brandenburg and Saxony-Anhalt from …
Economics Minister Mike Mabuyakhulu from the KwaZulu-Natal province in South Africa recently paid a visit to the Berlin-Brandenburg and Saxony-Anhalt regions. His purpose was to visit companies in the renewable energies sector to find out about the latest technological developments for a project in eThekwini/City of Durban. A strategic partnership with local networks means their members are now the preferred partners for this project. Berlin, 16/02/2012: At the start of February,

More Releases for MWp

solarhybrid AG: 'FinowTower II' solar power plant connected to the grid - total …
- 'FinowTower' solar power plant expanded by 60.4 MWp to 84.7 MWp - new capacity connected to the grid as scheduled - Allstedt I PV power plant (capacity 18.5 MWp) completed as contracted and in accordance with the Renewable Energies Act - Projects with a capacity of 218 MWp developed and realised by solarhybrid AG successfully completed at 11 locations in 3 countries in 2011 - over 1 million PV modules installed -
solarhybrid AG: reports that construction work has started on the 123 MW Vega so …
- All of the approvals for the 123 MWp Vega power plant in Italy have been received - Work has started on 39 MWp construction phase - completion and connection to the grid by the end of Q1 - To be marketed to investors after connection to the grid - Good prospects for 2012 based on a project pipeline for Germany and Italy with over 300 MWp Brilon, December 16, 2011: solarhybrid AG
solarhybrid AG develops 150 MWp solar power plant in Neuhardenberg, Brandenburg
- Real estate agreement concluded with Airport Development A/S for the former military airport - Preliminary planning approval to amend the land-use plan and the development plan given by the municipal council on December 14 - Connection to the grid planned in December 2012 Brilon/Neuhardenberg, 15 December 2011: solarhybrid AG is continuing its successful strategy of developing land at former military airports in Germany for the use for solar power plants. Following the
Solar park Thundorf (2.1 MWp) is connected to the grid
In Thundorf, Lower Franconia, 8,976 solar modules are now producing about two million kilowatt-hours of green energy per year. Dornach near Munich, November 2nd, 2010. In October, Gehrlicher Solar AG completed another photovoltaic installation 20 kilometres north of the city of Schweinfurt. Solar park Thundorf was connected to the grid on October 29th. After the completion, Gehrlicher will also be responsible for operation and maintenance of the park. The solar plant has
Gehrlicher Solar AG officially inaugurates largest solar power plant (25.7 MWp) …
Following the startup of the third construction stage, Lauingen Energy Park with a peak performance of 25.7 megawatts will be covering the yearly power requirement of 7,500 three-person households. Lauingen (Donau), October 10, 2010. On October 10, 2010, Gehrlicher Solar AG officially inaugurated Lauingen Energy Park. Following the completion of the last construction stage Helmeringen III in June 2010, this now largest solar power plant in Swabia will produce 28.98
Solea AG - Ground-Breaking Ceremony for the 5.67 MWp Solar Park in Köching (Sou …
On 27 October 2009, Solea AG celebrated the ground-breaking ceremony of the 5.67 MWp Solar Park Köching II. The investor is Terra Mundus Süddeutschland GmbH, a project company managed and advised by by Copex Investment Partners. Solea AG is the general contractor. The project is located in the municipality of Köching, between Aldersbach and Aidenbach, in the district of Passau. This project is a further milestone in the cooperation between